Project status
TABLE OF CONTENTS
- Columns on the status form and their meanings - Lump sum proposal items
- Columns on the status form and their meanings - Rates proposal items
- Non-default nominal account costs
- Coloring of proposal items
- Troubleshooting
This reference article explains all fields in the project status update window, with worked examples for both lump sum and rate proposal items.
Please make sure you have gone through the Record project status tutorial before continuing.
Columns on the status form and their meanings - Lump sum proposal items
On Lump sum proposal items, the main concept is the percentage of completion of works. It is mainly down to the project manager to define the percentage of completed works. Recorded hours from timesheet entries can help them define the percentage of completion of works when compared against the budgeted hours.

The table below explains each column with a separate worked example.
|
COLUMN NAME
|
DESCRIPTION | 09/11/23 | 09/30/23 | Difference 9/11 to 9/30 |
| ID | Proposal Item unique ID | 205166 | ||
| Name | Proposal Item name | Survey Building F5 | ||
| Department/ Service | Department/ Service where the proposal item is assigned to | Digital Engineering / Point Cloud (Processing) | ||
| Type | Defines whether proposal item is "Lump", "Rates" (automatic or with budget) | Lump | ||
| Costs | Cost of proposal item | £247.00 | ||
| Price | Price of proposal item (including overhead and profit) | £476.00 | ||
| Hours | Billable hours recorded from employee timesheets against this proposal item. Once the item has approved hours, the main figure shows the approved hours and a second line shows the hours still awaiting approval. Before any hours are approved, the figure shows all logged billable hours. 0% in the difference column means that no hours were recorded during the period. | 67.86% | 67.86% | 0% |
| Status | Percentage of completion (status) of proposal item according to the Project Manager of the project. On the September 11th 2023, we have used 67.9% of the allocated hours for completing 25% of proposal item works, and 32% on September 30th. Difference on status between the 11th and 30th of September is 7%. | 25% | 32% | 7% |
| Value | Kompass will calculate the value by multiplying the status percentage with the proposal item price. The difference between the selected dates shows the change in valuation between those dates. It is not the amount still to invoice: work in progress is the valuation minus the amounts already invoiced. | £119.00 | £152.32 | £33.32 |
Columns on the status form and their meanings - Rates proposal items
On Rates proposal items, the main concept is not the percentage of completion of works or the percentage of hours recorded. Instead we use the term "Units". Some examples of units could be:
- a day's work.
- an hour's work.
- all works and resources required to deliver a single product.
- all works and resources required to deliver a certain service, for example a drawing or a report.

The table below explains each column with a separate worked example.
|
COLUMN NAME
|
DESCRIPTION | 08/31/23 | 09/30/23 | Difference 8/31 to 9/30 |
| ID | Proposal Item unique ID | 205693 | ||
| Name | Proposal Item name | Bus stop survey | ||
| Department/ Service | Department/ Service where the proposal item is assigned to | Digital Engineering / Condition Building Survey | ||
| Type | Defines whether proposal item is "Lump", "Rates" (automatic or with budget) | Rate⥁ (automatic rate) | ||
| Costs | Cost of proposal item | $2,326.00 for 2 units that have been recorded in the latest status update. When PM is adding additional units, cost will be changing. The cost per unit can be also seen as $1,163.00. | ||
| Price | Price of proposal item (including overhead and profit) | $6,400.00 for 2 units that have been recorded in the latest status update. When PM is adding additional units, cost will be changing. The price per unit can be also seen as $3,200 | ||
| Hours | For rate items, these mark units and not hours. Therefore, if one unit includes 1 employee working for 9.5 hours against a proposal item and there are 19 hours recorded, Kompass will return 2 units. | 1 | 2 | 1 |
| Status | Units worked according to the Project Manager of the project. On the August 31st 2023, we have worked for 1 unit. On the September 30th 2023, we have worked for 2 units. Difference on status between those days is 1 unit. | 1 | 2 | 1 |
| Value | Kompass will calculate the value by multiplying status with unit price. The difference between the selected dates shows the change in valuation between those dates. Work in progress is the valuation minus the amounts already invoiced, so the difference is not necessarily the amount still to invoice. In this instance, $3,200 x 1 | $3,200.00 | $6,400.00 | $3,200.00 |
|
COLUMN NAME
|
DESCRIPTION | 08/31/23 | 09/30/23 | Difference 8/31 to 9/30 |
| ID | Proposal Item unique ID | 205691 | ||
| Name | Proposal Item name | Survey of Buildings | ||
| Department/ Service | Department/ Service where the proposal item is assigned to | Survey & UAV / Inspection (Traditional) | ||
| Type | Defines whether proposal item is "Lump", "Rates" (automatic or with budget) | Rate ⤒ (budget rate) | ||
| Costs | Cost of proposal item | £13,150.00 for all 25 units. Since this is a budget rate proposal item, that number will not change based on status. The cost per unit can be also seen as £245 and £281 for core and subcontractor nominal accounts respectively. | ||
| Price | Price of proposal item (including overhead and profit) | £14,050.00 for all set 25 units. Since this is a budget rate proposal item, that number will not change based on status. The price per unit can be also seen as £562 | ||
| Hours | For rate items, these mark units and not hours. Therefore, if one unit includes 2 employees working for 9.5 hours against a proposal item and there are 19 hours recorded, Kompass will return 1 unit. | 2.42 | 4.84 | 2.42 |
| Status | Units worked according to the Project Manager of the project. On August 31st 2023, we delivered 3 units to the client. On September 30th 2023, we have worked for 5 units. Difference on status between those days is 2 units. | 3 | 5 | 2 |
| Value | Kompass will calculate the value by multiplying status with unit price. The difference between the selected dates shows the change in valuation between those dates. Work in progress is the valuation minus the amounts already invoiced, so the difference is not necessarily the amount still to invoice. In this instance, £562 x 2 | £1,686.00 | £2,810.00 | £1,124.00 |
Hover over an "Hours" value to see more information:

In this example, 42.5 hours are budgeted. The 12 recorded billable hours account for 28% of that budget. The tooltip also breaks the hours into approved and unreviewed hours and shows the budget.
Non-default nominal account costs
Each proposal item can have staff, equipment and subcontractor/ other costs.
Depending on the setup of your organization, some subcontractor or other costs may be marked as subcontractor costs. They are not part of the core nominal account but sit in a separate subcontractor account. This helps the project manager see how costs are split between the two accounts and update the project status more accurately.
The "Costs" column shows a small badge when a proposal item has costs in more than one nominal account. An item with only default-account costs shows no badge. When badges appear, each shows the first character of the account name, and hovering over a badge shows the full name.
| Proposal ID | Core | Subcontract | Comments |
| 205693 | Y | N | only core works, so no badge is shown |
| 205696 | N | Y | only subcontractor works, so the badge shows the subcontractor account name's first character |
| 206591 | Y | Y | both accounts are included, so both badges are shown |
Coloring of proposal items
Proposal items come in three colors in the status update:
| Green | Lump sum proposal items that have reached 100% status and whose recorded hours did not change during the selected period. |
| Amber | Proposal items whose recorded hours changed during the selected period. Amber takes precedence over green. |
| White/ No highlight | Proposal items with no change in recorded hours, other than completed lump sum items. A rate item does not turn green when it reaches its budgeted quantity, and a status change alone does not turn a row amber. |
Status update date restrictions
Status updates have strict date validation rules. These constraints are important for project managers to understand, particularly when recording status just before project delivery:
- For lump sum items, the status date must be strictly before the project's delivered date.
- For rate items, the status date must be on or before the project's delivered date.
- Status dates cannot be after a proposal item's closed date.
- Status dates cannot be on or after the project's abandoned date.
Important: When a project is marked as delivered, Kompass automatically inserts a virtual 100% status entry for each accepted lump sum proposal item. This means the project will show full value for all accepted lump sum items at delivery, even if no final status update was recorded manually. Unaccepted lump sum items have no statuses and do not gain full value at delivery. This is important context for project managers to understand so they are not surprised by an automatic status entry appearing on delivery.
Troubleshooting
-
No staff resources
Each proposal item can have costs for staff, equipment and subcontractor/ other costs.
The only cost that can be directly linked with working hours of employees is the staff cost.
If hours are recorded against a proposal item that has no staff costs, Kompass shows a warning.
An exclamation mark in the Hours column means the proposal item has no hours budget set. Hover over the exclamation mark to see the explanation. In this example, the warning shows 4 recorded hours against the item. To resolve this, click the affected proposal item.

Edit the proposal item and add at least one staff cost. The Staff Costs card shows No items when the item has no staff costs yet. Make sure the price of the proposal item is still correct after adding the staff costs.

Click Save and go back to the status update of the project. The item now has a staff budget, so the exclamation mark clears and the recorded hours count against that budget.
-
Exceeding budgets
Automatic rate proposal items have no threshold: the project manager can keep adding units while the project runs. A lump sum proposal item cannot exceed 100% status. Hours can exceed 100% if the project overruns, but status cannot. If you try to enter a higher percentage, Kompass warns you and limits the input to 100%.
Kompass also warns you if you try to exceed the budgeted rates on a budget rate proposal item. In the example, the item allows 25 units and you tried to add 32.
The difference is that Kompass allows the excess units but shows an exclamation mark to tell you that an updated proposal is needed for your client. WIP also includes the excess units.
- Hours shown not matching the hours recorded
A common question from project managers is why the Hours figure shown in the status table does not match the total hours they can see in the Timesheets section of the project's Operations tab or in employee timesheet exports. The reason is that the Hours column in the status table shows billable hours only.
What counts as a billable hour?
An hour recorded in the timesheet counts as billable in the status table only when the task, the proposal item and the project are all billable:
- The Task the hour was logged against has a billable task type.
- The Proposal Item the task belongs to is billable.
- The Project itself is billable (its category is set to billable, and the billing client is not flagged as internal).
If any one of these conditions is not met, the hours are recorded normally and will appear in the employee's timesheet and in the project's Operations tab, but they will not be counted in the Hours column on the status update.
The figure can also differ from the total recorded hours for other reasons: draft and rejected timesheet entries contribute no billable hours, time recorded as non-billable is deducted, and the organization's break and travel settings can change how many of the recorded hours count as billable.
Practical example
Suppose a project manager looks at the status for a proposal item and sees:
- Operations tab (all timesheet entries): 40 hours
- Status table Hours column: 32 hours
The 8-hour difference can have several causes, not only a task, proposal item or project that is set to non-billable:
| Reason | Where to check |
|---|---|
| Hours were logged against a task whose task type is set to non-billable | Kompass Admin → Tasks → Types → check the Billable flag |
| Hours were logged against a proposal item whose service or department is set to non-billable | Kompass Admin → Company → Services or Departments → Billable flag |
| The project category is set to non-billable | Kompass Admin → Projects → Categories → Billable flag |
| The project's billing client is flagged as internal | Project → Billing Client → Internal flag |
| Hours were logged on a draft or rejected timesheet entry | Timesheets → check the entry status |
| The entry was recorded as non-billable | Timesheet entry → Non-billable |
| Breaks or travel are configured differently for billable hours | Kompass Admin → Diary → Configs → Hours billable include |
What does this mean for your status update?
You enter the completion percentage for a lump sum item, or the number of units for a rate item. Kompass calculates the value from that quantity and the item's price. Recorded hours provide a comparison against the budget; they are not the source of the status percentage or valuation.
If non-billable hours are being recorded intentionally (for example, internal time, admin, or charitable work), this is expected behavior and the Hours figure in the status table will always be lower than total timesheet hours.
If the difference is unexpected, for example, hours that should be billable are appearing as non-billable, check the settings and entry states listed above.
Seeing the full breakdown
Hovering over the Hours value in the status table shows a tooltip with a detailed breakdown:
- Budget: the hours budget per unit (or for the full proposal item on lump sum items).
- Approved: billable hours that have been approved by a timesheet approver.
- Unreviewed: billable hours that have been recorded but not yet approved.
- Total: the combined billable hours (approved + unreviewed).
Note that this tooltip always shows billable hours in both columns. If you need the full total of all hours, including non-billable time, open the Operations tab of the project, which lists all recorded timesheet entries without the billable filter applied.